Aeris Global Progress at Tatua Dairy Wastewater Treatment Plant

Aeris Global commenced delivery of equipment last week for Stage One of the new Tatua Dairy Wastewater Treatment Plant. The first consignment included eight 110kW aquaturbo® Model
AER-AS Floating Surface Aerators
.

Main Contractor, MAP Projects is making excellent progress with construction of the two 15,000m3 lagoons despite challenging weather. Each lagoon will be installed with four aerators.
Stage Two of the project will increase the total aeration energy from 880kW to 1,320kW

The plant will include the full complement of Aeris products and accessories including the popular otterdock® – Safe Docking Platform. otterdock® allows personnel to retrieve
equipment to the safety of the platform rather than going on the water. The plant also features
aerisanchor® – Multi-function Mooring System and aercable® – Cable Management System.

The Aeris Global Field Services crew plans to get established on-site and commence installation in Q4.